Procurement, design and construction process

DESIGN PHASE

CONSTRUCTION PHASE

HOME DECORATION
AND NETWORKS


20% payment
Internal communication networks, interior and facade decoration are being built.

HOUSE FRAMEWORK CONSTRUCTION

30% payment for finishing.
A house is being built, waterproofed and insulated

STARTING CONSTRUCTION

40% advance payment before construction begins for the procurement of materials

PROJECT SELECTION

Choosing a building type according to function

CONCLUSION OF THE CONTRACT

We agree on the details of the order, the project is adjusted, and a contract is signed.
Advance payment of 5%

ROW


Sometimes we can start building construction immediately, sometimes we have to wait in line for up to 2 months.

WINDOW DELIVERY


Windows are manufactured and delivered within 4 weeks of placing the order.

SITE SURVEY

The object is surveyed - the approach, the desired location of the house. We agree on the ideal option.

CONSTRUCTION SITE
PREPARATION


The construction and preparation of the foundation and utilities (water, sewage, electricity) is underway. Access has been facilitated.
Engineering communications can be constructed and connected even after the building is delivered.

DELIVERY**


The building is delivered and placed on the foundation.

PROJECT COORDINATION

If necessary, a simplified procedure for project coordination with the municipality is established. Review within 10 days, coordination takes up to 2 months.

Day 1

Day 3 - 5

Day 1 - 3

Day 20 - 40

Day 1 - 3

n days

Day 4 - 45

Day 18 - 28

Day 40 - 45

Day 5 - 10

Day 4 - 18

* Preliminary purchase process and lead time, depending on the type of house, planned location, and occupancy.

** If the house cannot be delivered as a whole, we can build it on site or deliver the house in parts

Before buying a house

Buying a home is a big step and a responsible purchase. Below we have compiled some tips and suggestions that are worth considering before purchasing a home.

Contact us if you have any further questions.

PERMITS

Make sure what documents and permits will be required when starting construction. Our industrially manufactured buildings can be coordinated with the building authority using a simplified procedure by submitting an explanatory note.

HOME DELIVERY OPTIONS

One of the most important factors is access to the desired location. We deliver houses with a special platform, the total height of which does not exceed 5m, and the width is 4m. If access is difficult, we offer to deliver the house in parts, assembling its panels on site.

HOUSE PRICE and COMPLETION DEGREE

Choose a building not only by price and quality, but also by its level of completion. For example, our competitors often do not include the roof, exterior decoration, etc. in their prices. In the end, the total price of the building is much higher.
the initial budget.

QUALITY CONTROL

Pay attention to the fact that high-quality and high-value construction materials are used in the construction process of the building. Over the years, we have selected the highest quality, most aesthetic, most durable, and most long-lasting materials that we use in construction.

ALL-SEASON HOMES

If the building is planned to be inhabited in winter, the amount of insulation and the way it is insulated are important. For the insulation to work effectively, the building must be properly insulated. We insulate buildings so that they are habitable all year round and so that the insulation does not significantly reduce the living space.

TRUST THE PROFESSIONALS

Choose a reliable building manufacturer with experience. With us, ECOSPACE, you will always receive the highest quality, customized deadlines and consultations on issues of interest to you.

Financing options for buying a house. Modular houses on installments. Modular house loan.
Financing options for buying a house. Modular house on installments. Modular house loan.
bottom of page